A laser cutting quote is arithmetic, not guesswork. Every price a small shop sends out, whether it was worked out on a spreadsheet or in someone’s head, is built from the same handful of parts: the material the job uses, the time the machine spends cutting and piercing, a setup charge, a margin, and a floor below which the job isn’t worth doing. This guide walks through each part in the order you would calculate it. A worked example follows at the end.
The formula in one view
material cost = area used × thickness × density × price per kg
cut time = cut length ÷ cutting speed + pierces × pierce time
machine cost = cut time × machine hourly rate
part cost = material cost + machine cost + extras per part
order price = max(minimum charge, (setup fee + quantity × part cost) × (1 + margin))
then apply any quantity breakEvery input on the right-hand side is a number your shop owns. None of them should come from a generic chart you found online. Your speeds depend on your machine’s power, your assist gas, your nozzle and how you tune your cut parameters.
Step 1: Measure the part
From the customer’s DXF you need four measurements:
- Cut length: the total length of every contour that will be cut, outer profile plus every hole and slot.
- Pierce count: usually one per closed contour. A plate with a profile and six holes has seven pierces.
- Bounding box: the smallest rectangle around the part. You need it to check that the part fits your bed and sheet sizes.
- Net area: the outer area minus the holes. This is the material that leaves the shop as a finished part.
Before you trust any of these, check the file. Wrong units, dimension lines on the cut layer, duplicate lines and open contours all distort cut length and pierce count. Our guides on fixing DXF units and open contours cover the usual traps.
Step 2: Material cost
A part consumes more material than its own area, because of the skeleton left between parts and around the sheet edge. The simplest honest method is to divide the part’s area by a utilization percentage, meaning the share of a sheet that typically ends up as parts in your shop. Multiply the area used by the thickness to get volume. Multiply by density to get weight, then by your price per kg.
Mild steel is commonly taken as 7.85 g/cm³ (7,850 kg/m³) and aluminum as about 2.70 g/cm³. Use your supplier’s figure if it differs. Some shops price by the sheet instead. If you do, charge the fraction of the sheet the job uses, or the whole sheet if the customer’s quantity uses most of it.
Step 3: Machine time
Cut time has two parts. Cutting: cut length divided by your cutting speed for that material and thickness. Piercing: the number of pierces times your pierce time for that material and thickness. On thick plate with many small holes, piercing can take longer than cutting. That’s why quotes based on cut length alone underprice perforated parts.
Real machines slow down in tight corners and small features, so a speed from a cut chart is an upper bound. Many shops apply a factor to cover this. The cleanest way to find that factor is to compare a few past jobs’ estimated times with the times actually logged on the machine.
Step 4: Machine hourly rate
Machine cost is cut time multiplied by an hourly rate that covers the machine, its power and gas, maintenance, the operator and a share of overhead, divided by the hours the machine really runs. That rate deserves its own calculation. See how to work out your laser hourly rate.
Step 5: Setup, margin and minimums
- Setup fee: covers programming, loading the sheet and first-part checks. It is charged once per order, not per part.
- Margin: applied on top of cost. Keep it separate from the hourly rate so you can see what you actually earn.
- Minimum charge: the smallest invoice worth the interruption. A single small bracket can take as much handling as a batch.
- Quantity breaks: because the setup fee is spread over more parts, per-part prices fall as quantity rises. Many shops also add a discount tier for repeat volume.
A worked example
Hypothetical inputs, not benchmarks. Use your own machine’s values. A mild steel bracket, 3 mm thick, quantity 50.
- Net area 0.020 m², utilization 75% → area used 0.0267 m².
- Weight: 0.0267 m² × 0.003 m × 7,850 kg/m³ ≈ 0.63 kg. At $1.50/kg → material ≈ $0.94.
- Cut length 1.2 m at an assumed 2.0 m/min → 36 s. Six pierces at an assumed 1 s → 6 s. Total 42 s.
- At an assumed $150/hour machine rate: 42 ÷ 3,600 × 150 ≈ $1.75.
- Part cost ≈ $0.94 + $1.75 = $2.69.
- Order: ($40 setup + 50 × $2.69) × 1.25 margin ≈ $218.13. That is above an assumed $75 minimum, so the minimum doesn’t apply. About $4.36 per part.
Run the same calculation for quantity 5 and the setup fee dominates: ($40 + 5 × $2.69) × 1.25 ≈ $66.81. The minimum then lifts it to $75. That jump is exactly what a quantity-break table should make visible to the customer.
Check the method against your own history
Take three to five jobs you’ve already quoted and won, run them through this formula with your current inputs, and compare. If the formula comes out consistently low, something is missing. The usual culprits are pierce time, a minimum you always apply in practice, or a stale material price. Fix the input, not the answer. Once the formula reproduces your past quotes, you can trust it on new ones.
For other processes, see how plasma and waterjet change the cost drivers. The blog goes deeper on minimum charges and setup fees and quantity price breaks.